What is the process for getting SRS (Software Requirements Specification) approval?
Get the list of acceptors, hold a walkthrough meeting, have the customer fill a sign-off protocol, circulate review items as a "last chance to object," then incorporate changes as a new version and resend.
SRS Approval Process:
-
Get the list of acceptors from the PM/customer
- Who needs to sign off?
-
Organize an SRS walkthrough meeting with the acceptors
- Review the document together
-
Customer must fill out a sign-off protocol
- Final remarks/feedback
- Conditions for sign-off
-
Before incorporating changes, send a list of the review items to the acceptors
- Include those who did not attend the meeting
- This is the "last chance to object"
-
Incorporate the changes (save as a new version) and send it to the customer
Key point: Get formal sign-off before development begins - this protects both parties and establishes a baseline.